. Transnet Multi Product Pipeline project expenditure is at 25 percent to date and this very is worrying considering the need to ensure security of petroleum supply for the Country. The delays were caused by the Environmental Impact Assessment processes and land disputes that occurred in areas where the pipeline is being constructed. The project is understood to be running behind schedule by nine months. There is also possibility that the delay may result in costs escalation of the project if it is not managed well.