(a) The original contract commenced on 13 November 2011 and the contract was terminated (DPW) on 13 March 2014 due to the contractor not performing his obligations. The second contract to finalise the outstanding work was awarded on 10 November 2015.
(b) The contractor failed to perform his obligations and the National Department of Public Works had to re-start the tendering process in order to appoint the new contractor for completion of the project.
(c) The anticipated date of completion is 9 July 2016.
(d) The budget allocation for the construction and completion of the specified police station is R 31 581 451-00.
(e) The amount spent to date is R 16 887 830-00.
(f) The projected expenditure for the project is R 31 581 451-00.