(a) The Bucket Eradication Programme is being implemented in the Northern Cape, Free State, North West and Eastern Cape Provinces, and the progress is indicated in the table below:
Province |
Targets |
Units Completed |
Flushing |
Not yet Flushing |
Remaining to be constructed |
Northern Cape |
7618 |
7056 |
3685 |
3371 |
562 |
Eastern Cape |
3319 |
3269 |
2919 |
350 |
50 |
North West |
223 |
223 |
223 |
0 |
0 |
Free State |
13880 |
13698 |
1827 |
11871 |
182 |
|
25040 |
24246 |
8654 |
15592 |
794 |
(b) Below are reasons for the delay in the completion of the specified programme: