(1)(a) The pipeline project between the Craigieburn Dam and Greytown in KwaZulu-Natal started on 24 March 2015.
(1)(b)(i) The budgeted cost of the project was R203 802 607 including escalation, contingencies and VAT.
(1)(b)(ii) The distance of the pipeline is 35.0km
(2)(a) The project has not been completed due to poor performance of the three contractors appointed in the project which resulted in termination of the contracts.
(2)(b) It will take about eleven (11) weeks to complete the outstanding scope of the works. The actual start and completion dates will be negotiated between uMzinyathi District Municipality and the prospective replacement contractors once appointed through Section 32 of the Municipal Supply Chain Management Regulations.
(2)(c) The cost of the project to date is R79 493 188.
(2)(d) The total estimated cost to complete the project is R138 647 000.
(3) Yes, the project went out on tender.
(3)(a) The companies that made submissions for the specified tender are as follows:
Bankuna Engineering |
V. Bhengu Construction |
Sizabonke t/a Pilcon Projects |
Moray & Dickson Construction |
Shula Construction |
Nongafa Construction |
Igugulabafazi Developments |
Soundrite Construction |
JMngcwango Trading |
Valente Bros (Pty) Ltd |
Barleda 65 cc JV Busizwe |
Ntandoyami JV |
Velakude Trading JV Ugwadule Trading |
R&B Pipelines JV Sikoti |
TBA Construction |
Blue Dot G Services |
F&A Civils |
Thembalethu Civils |
Anvisba Civils |
Lenong Azishe JV |
WK Construction |
Velekude JV Umzuzu cc |
Cycade Pipelines |
AM Pomolong JV |
WBHO Construction |
Tshenolo Resources JV Kufiki |
Namandla Roads & Civils |
Esor Construction |
Cerimele Construction |
Phumi JV Ishishini |
Zanamanzi Services |
(3)(b) The pipeline was broken into three contracts, and the contractors awarded the tenders were Soundrite Construction, Bankuna Engineering and Phumi/Ishishini JV.