(i) Phase 1 The process of upgrading will commence with the following: Sewer Network, Potable Water Network, Storm Water Control, Road upgrades, Solid waste disposal and Cable ducting. The total costs and duration estimated for Phase 1 and Phase 2 is R130 million. The estimate for phase 1 was R52 million and the tender price was R42 million. Phase 1 will take approximately a year. The duration of phase 2 will be confirmed after the second tender process had been finalised.