The KHLM said that the balance of the MSIG grant has been reserved for the revision of the new valuation roll which was implemented in July 2009. The KHLM reported that all claims of the contractors and consulting engineers have been paid using the MIG. However, the KHLM reported that the project has been delayed due to a rock formation which was found while it was excavating the soil. The consulting engineering company, called KV 3, has indicated that the project will be delayed for a long period.