Hon Minister, thank you for the answer. I think you have read me correctly. From internal Eskom documents addressed to the chief executive officer, Mr Jacob Maroga, it is clear that there were serious problems with the whole tender process at Medupi.
To give you a few examples - and I will quote from the document - there were procurement processes that did not adhere to the supplier pack, detailed cost estimation was thin, water capacity is constrained, Eskom committed to detailed boiler specification without coal being succeeded, and so on. I can go on, Madam Minister.
In light of the above, does the Minister consider appointing a commission of inquiry to investigate this whole process, as it seems to be another example of bad management by Eskom?