(1)With reference to the 59,1% underspend in respect of his department’s Programme 6 in the first quarter of the 2017-18 financial year, what amount has actually been spent to date on the (a) Critical Infrastructure, (b) Manufacturing Development Incentives, (c) Service Sector Development Incentives and (d) Special Economic Zones Programmes;
(2) have (a) the delays caused by outstanding compliance documentation required for the processing of claims and (b) claims that failed to comply with the guidelines been rectified in each case; if not, in each case, (a) why not and (b) what steps have been put in place to rectify the situation; if so, are there any further foreseen causes for future delays?NW3376E