(a) R600 is Main Road P212 which is 34km under Okhahlamba Local Municipality; the
bi) Departmental has been maintaining the road by means of the following activities:
b) Main Road P212 is due for Heavy Rehabilitation and design is schedule to commence in the first quarter of 2018/19 financial year in order to start Phase1 Construction in the third quarter of the 2018/19 financial year.
c) The Rehabilitation of Phase 1 is anticipated to commence in the third quarter of 2018/19 financial year.
d) The project cost estimate is R 161.8 million for Rehabilitation of 34kilometres in three financial year.
e) The Department will advertise the contract through open tender to get contractor to rehabilitate the road.