1) There is no new flue gas desulphurisation plant being constructed, but the temporary stacks were constructed to allow continued operation of Units 1, 2 and 3 while the repairs on the existing permanent stacks are being conducted. The work has commenced, and the targeted completion date is 31 December 2024. The exemption granted by the DFFE is up to 31 March 2025.
(2) Eskom has entered into a long-term contract with the FGD plant's Original Equipment Manufacturer for operation and maintenance, including technical support.