(1) With reference to the construction of a temporary chimney at the Kusile Power Station to bypass the desulpherisation process to bring Units 1 and 3 back online, by what date is it envisaged that construction on the new wet flue gas desulpherisation plant at the specified power plant will commence;
(2) Whether the design flaws that led to the buildup of slurry that caused the collapse of the plant have been rectified yet; if not, by what date is it envisaged that the design flaws will be rectified; if so, what are the relevant details?