. Project 1 and 2: The construction of aprons around the houses was complete. At the time of the visit, the V-drain was under construction. . Project 3: Houses in Kranshoek had been repaired, plastered and painted. . Project 4: In Green Valley, 13 out of 15 houses that were demolished had been rebuilt, and others houses repaired. . Project 5: Upgrading of infrastructure of the Kranshoek project was delayed until additional funds were approved. Excavation for storm water drainage pipelines were under construction. . Project 6: Upgrading of civil services in Green Valley was terminated due to non-performance by the contractor and re-awarded to Ukhana Projects. Excavations for the storm water draining were under construction.